Stage one: survey the rooms and the whole route
The first visit should define the problem: which rooms overheat, when they are occupied and whether cooling, heating or both are required. Glazing, orientation, insulation, people and equipment inform the capacity recommendation.
The survey then follows the physical route from indoor unit to outdoor unit. Wall construction, pipe length, condensate fall, electrical supply, isolation, boundary position and future service access are resolved together rather than treated as separate surprises.
Stage two: issue a scope that can be checked
The quotation should name the proposed equipment and capacities, show the quantity and position of indoor and outdoor units and state how pipework and drainage will be finished. It should also identify any pumps, brackets, bases, access equipment or electrical work included.
Clarify exclusions before accepting: decoration, unusual making good, scaffolding, supply upgrades and builder work should not appear as assumptions after the date is booked. A clear scope is the reference for both the customer and installation team.
Stage three: protect the property and set out the positions
On arrival, the team should confirm the agreed positions and route, protect floors and furniture and check for any site change since survey. The mounting plate, core hole and outdoor supports are then set out against the confirmed dimensions.
A late change of unit position can affect drainage, pipe length, cable route, sound and appearance. If the agreed design cannot be followed, the consequence should be explained before drilling continues.
Stage four: install the indoor, outdoor and connecting services
The indoor unit and outdoor condenser are fixed to suitable supports. Refrigerant pipework, interconnecting cable and condensate drainage are installed along the agreed route, with external containment and insulation finished so they remain weather-resistant and serviceable.
Gravity drainage is preferred where the route allows it. A condensate pump may solve a difficult position, but it adds a component, operating sound and maintenance requirement that should have been visible in the quotation.
Stage five: pressure test, evacuate and commission
Split systems containing or designed to contain fluorinated refrigerant must be installed by appropriately certified people and businesses. The refrigeration circuit is pressure-tested using the specified method, evacuated to remove air and moisture and then completed according to the manufacturer instructions.
Commissioning confirms operating modes, temperatures, airflow, drainage, controls and any manufacturer checks. This stage is not optional tidying-up: it is where the installed system is proved and recorded before handover.
Stage six: handover and aftercare
The customer should be shown how to use cooling, heating, fan and schedule functions, how to clean permitted user filters and what not to remove. Warranty registration, servicing expectations and the route for reporting a fault should be clear.
Before the team leaves, compare the completed work with the written scope: positions, containment, drainage, making good and controls. Photographing model labels and keeping the quotation, commissioning and warranty information together makes future servicing easier.
How long will the work take?
A straightforward single-room installation is often completed in one working day, but access, wall construction, electrical work, pumps and route length can change that. Multi-room systems, high-level equipment and concealed first-fix work need a project-specific programme.
The reliable answer belongs in the quotation after survey. Ask which rooms will be unavailable, whether power must be isolated and what must be moved beforehand so the estimate includes the actual site conditions.